In this sample, we will input the result from the Resource Gantt Chart. Right-click on Operation 01:10 and select Operation, then Results.
This operation is done, so we will change the status to Completed. Click Ok.
A gray underline will be displayed in the operation and the slant lines will show the progress of the operation.
Do the same for operation 3:10 and input the result. Let’s assume that this operation has been delayed from the plan. Enter the reported start time as 2016/11/1 13:00. Input 7,000 in the reported quantity. Then, click Ok.
The result input is done.
You can also input the result from the Operation table aside from the Resource Gantt Chart. If you enter the result to some operations, you may use the Operation table.
To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 23. User Interface).