In this sample, we will create a new schedule with the result input and change it to scheduling layout for confirmation.
Go to View tab, then Layout Setting, select Scheduling.
To change the scheduling basis time, drag and drop the scheduling basis time to November 3rd.
You will see that some operations were assigned in the past by moving the date.
The progress of the operation can be seen through the slant line. You will notice also that a part of the operation 3:10 with no slant lines was also assigned in the past and is delayed.
Next is to reschedule and reflect the results and re-assign the operations. The scheduling results will be changed and will be seen near the scheduling basis time. Run the reschedule button. You will see that the released operations that were not started are shifted to a future time.
The 3:20 operation now matched the delay of the previous process and shifted to a future time since the previous process 3:10 was delayed with the original plan.
To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 23. User Interface).