In Asprova, you can set the status of the operations as either Released or Completed. In this sample, operations have been rescheduled and adjusted. Now, we will change the status of the operation that has been scheduled to start by November 3rd to be released.
Click on the area that has no operation bar on the resource Gantt chart and drag to select the range.
Select the operation which is scheduled to start on November 3rd. Right-click on the selected operation and select Status, then choose Release. The status will change to Released.
If for whatever reason you made a mistake in the changing of status, you can easily remove the status to Unfreeze.
In addition, you can save the state of the window as a Layout.
Now the schedule which can put out instructions is completed. Save the project file for future reference.
To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 23. User Interface). You may also check Online Help on Status.