From the previous article, if manual adjustment does not address the delay in the order, maybe there is not enough time for the operation to assign. We can try to increase the working time and see if this eliminates the delay.
In this sample, we will change Nov 5, a Saturday as a working day. Left-click on Nov 5 while holding down the shift key.
Right-click the cell which is highlighted and then choose Day shift.
You will see that the shift of Nov 5 has changed to a Day Shift.
Run the reschedule button and you will see that operations will be assigned on Nov 5.
You can look at the message window and confirm that there is no more message about the delay. This means that the delay was eliminated.
To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 23. User Interface). You may also refer to the online help for more details on Calendar settings.