Operation Split

There are two methods on how to split the operations. One of them is to register the lot size for the equipment. In this sample, input 200 as the Resource split size MAX in the equipment Cutter 1.

Asprova1

This method is used when the quantities, which can be processed, are different for each piece of equipment. Run the reschedule button and you will see that the operations have been split.

Asprova2

During the assignment of operations, which were split as mentioned above, the corresponding instructions can be assigned separately.

Furthermore, it is also possible to shorten the lead time, by setting the Time constraint method as “ESE”.

asprova3

Run the reschedule button and you will see that the operation has been finished earlier than the previous sample.

Asprova4

Another method of operations splitting is to register the Production lot size MAX for each item at the [Item table].

Asprova5

When the production quantity is larger than the lot size of the item, the operations will be split and then assigned.

Asprova6

This is used when the production quantities are different for each item.

Also, when there are several pieces of equipment, parallel production becomes possible and can reduce lead time. This can be done by changing the Time constraint method to “SSEEE”.

Asprova7

Asprova8

Note also that the operation split function has plenty of effects, such as split by rate, switching workers by shift, etc.

To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s online help and search Operation Split or its e-Learning videos at http://lib.asprova.com/ (see 24. Scheduling Logic).

 

 

Discover more from The World's Best Factory in the Asian Era

Subscribe now to keep reading and get access to the full archive.

Continue reading