Set up Time (Resource)

In Asprova, it is also possible to schedule the setup time for changing molds and jig tools. This can be specified in the Integrated Master Editor. This article will show you how to generate a schedule setup by switching the main resource and the sub-resource.

In this sample, we will produce item “AX”. Press 1 will be used as a main resource. Mold 1 and Mold 2 will be used as a sub resource.

asprova1

Let’s register in the Resource setup table a 120m-setup-time to switch Mold 1 to Mold 2 on Press 1.

asprova2

In addition, let’s set a 20m-setup-time to switch Mold 2 to Mold 1.

asprova3

Press the reschedule button to see the result. At the Resource Gantt chart, you will see that there is a 120m-setup-time on Press 1 when Mold 1 to Mold 2 is switched. Subsequently, there is a 20m-setup-time on Press 1 when we change Mold 2 to Mold 1.

asprova4

To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 24. Scheduling Logic).

free_trial_button2

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: