Change Status to Release – Resource Gantt Chart

In Asprova, you can set the status of the operations as either Released or Completed. In this sample, operations have been rescheduled and adjusted. Now, we will change the status of the operation that has been scheduled to start by November 3rd to be released.

Click on the area that has no operation bar on the resource Gantt chart and drag to select the range.

Asprova1

Select the operation which is scheduled to start on November 3rd. Right-click on the selected operation and select Status, then choose Release. The status will change to Released.

Asprova2

If for whatever reason you made a mistake in the changing of status, you can easily remove the status to Unfreeze.

Asprova3

In addition, you can save the state of the window as a Layout.

Asprova4

Asprova5

Now the schedule which can put out instructions is completed. Save the project file for future reference.

To learn more about Asprova specific to this sample demonstration, you may visit Asprova’s e-Learning videos at http://lib.asprova.com/ (see 23. User Interface). You may also check Online Help on Status.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: